The Brăila–Galați Express Road (DEx6) will not open this year after essential components for its cable-stayed bridge over the Siret River were stolen, despite the project being nearly complete, Adevărul reported. The road was initially due to open in 2023.

Galați County Police said on Thursday that they had opened a criminal case for theft after cable anchor components and related parts went missing from the bridge construction site. Initial police checks indicate the thefts began in late 2025 and continued until now.

Romanian contractor UMB, which has worked on the project since 2022, filed a complaint with police. More parts have since disappeared, and replacing the stolen components will not be possible by the end of the year, CNAIR spokesperson Alin Șerbănescu told Adevărul.

“The constructors filed a complaint with the Police. They also have a security company there, or had one. The constructors need to clarify the matter with both the Police and the security company. What is certain is that, because of the theft, although the Brăila-Galați Express Road is 99% complete, an important component is missing: the bridge’s cables.

“Work cannot advance because, on cable-stayed bridges, the structural elements are supported by these cables, and construction progresses as they are installed. Without the cables, the bridge risks giving way, collapsing,” Alin Șerbănescu added.

The 10.77-kilometre express road was originally scheduled for completion in 2023, but its deadline has been postponed several times. The project includes an almost two-kilometre stretch made up entirely of structures, including viaducts, a metal arch bridge over the railway and the cable-stayed bridge over the Siret.

“It is the most spectacular work in terms of structures, apart from the tunnels being built on the current network,” Ionuț Ciurea of Pro Infrastructura told HotNews.

The road is designed for speeds of 120 km/h and has a 22-metre platform. The project also includes two bridges over irrigation canals, two viaducts, a roundabout and widening a 0.43-kilometre section of the existing DN28 from two lanes to four, from Galați to the express-road junction.

The project specifications list UMB as the contractor, a value of 372 million lei and a contract signed in April 2021. The contract allowed 34 months—10 for design and 24 for construction. Works began in December 2021 on a seven-kilometre section, with authorisation for a further three kilometres in the bridge area issued in December 2022. The listed original deadline was December 2024, later extended to December 2025. Physical progress was reported at 95.5% in November 2025.